Who wants to take bets I won't get done what I want to?
We're going to have some seriously warm weather, like 65* Christmas Eve and Day.
My plan is to hit all of the trusses with my pressure washer, finish exterior sheeting, build the eaves, and straighten/block the upper portion of the trusses.
I also ordered 95% of EVERYTHING for the outside. The rest of the sheeting, all roofing materials, all siding (including corners, j-channel, etc) and even all of the shutters. $6,200. I need to update my spreadsheet and see how far in the hole I've gotten. I think I'm up to 40K now (with everything ordered).
That still leaves labor for roof, electric, doors, insulation, sheetrock, and finishes.
Maybe I should have just done a metal building